NPU W Atlanta Department of Transportation Monthly Project Dashboard Report

In addition, here’s a quick status update on projects in design and construction:

Atlanta Ave (TCC)

Final utility design expected from Georgia Power Company this fall.  Overall design is on hold until funding source is confirmed.

Boulevard (TCC)

Final utility design expected from Georgia Power Company this fall.  Overall design is on hold until funding source is confirmed.

Glenwood Rd (TCC)

Final utility design expected from Georgia Power Company this fall.  Overall design is on hold until funding source is confirmed.

R.D. Abernathy/Georgia Ave (TCC)

Final utility design expected from Georgia Power Company this fall.  Overall design is on hold until funding source is confirmed.

Monroe/Boulevard (TCC)

This corridor is included in a package of citywide signal upgrades.  The project manager is evaluating alternative routes to expedite procurement.

Glenwood LCI Match (Realignment at Moreland)

Construction is underway.

Ayr St Roadway Construction

This project is being bid as a part of the Unpaved Roadways Phase I package originally bid at the end of December 2019.  Bid documents are in procurement for rebidding.

Braeburn Roadway Construction

This project is being bid as a part of the Unpaved Roadways Phase I package originally bid at the end of December 2019.  Bid documents are in procurement for rebidding.

South Boulevard Complete Streets

This is a concept design-only project. Concept design is underway.

Neighborhood Sidewalk & ADA Improvements

Original scope is complete; however additional work been added to the contract that will be completed this fall.

Right of Way Acquisition and Install Lighting (Atlanta  Beltine) 

67.5% of total funding allotment has been paid; annual payments will continue until funding commitment is complete.

Downtown Special Events ITS

Most work completed on this citywide contract; will cover signal tech and traffic engineering work needed for Dekalb Ave Safety Improvements.

Signal Optimization and Detection Phase I 

Most work completed on this citywide contract; will cover signal tech and traffic engineering work needed for Dekalb Ave Safety Improvements.

Smart Signal Systems Phase I

Most work completed on this citywide contract; will cover signal tech and traffic engineering work needed for Dekalb Ave Safety Improvements.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s